This project is installing new steel stairways and field access improvements on Fields #1, 2, and 3 in the North Tahoe Regional Park. This project will replace the old wood stairs that were at the end of their functional life.

In 2022, paver plazas at the top and bottom of the stairway and ramp to Fields #2 & #3 and the top of the stairway to Field #1 were installed. Construction of the ramp is complete, and the steel stairways are underway.

The contractor is returning to the Regional Park in May to complete the stairways and finish the project.

Estimated Cost: $340,950.40

Estimated Completion Date: June 2023