This project will construct approximately 7,600 linear feet of new watermain in the Golden Avenue, Rainbow Avenue, Steelhead Avenue (partial), and Secline Street rights-of-way in Kings Beach, see image below. The new watermain will replace the existing small-diameter watermains located along the back of the properties and provide fire hydrant coverage to all properties within the project area in accordance with the California Fire Code.

Construction is scheduled to begin in May 2023, dependent on the weather/snowpack.

Estimated Cost: $3,981,642

Estimated Complete Date: October 2023


PROPERTY OWNER SERVICE RELOCATIONS

Detailed information for property owners is available via this link – Kings Beach Waterline Service Relocations

  • Property owners currently served by an old watermain in a backyard easement will be required to relocate their water service and connect to the new watermain.
  • The District will install a new point of connection (meter box and customer shut-off valve) at the property line facing the street; however, the construction of the new water service from the building to the new point of connection is the responsibility of the property owner, as outlined in NTPUD Ordinance #361.

Kings Beach Waterline Service Relocations


 