Water/Sewer

Click image to view more photos
Click image to view more photos
Click image to view more photos

The Capital Improvement Program (CIP) directs utility line replacements and specific projects to address current and projected needs of the community’s water and sewer system. Following is a list of Current Projects underway and projects recently completed. Recent bid results are available here.

When the District must relocate the point of service connection for a property, it is the responsibility of the property owner to move their service (water or sewer) to the new point of location.  Additional information on this policy can be found by clicking here.

Current Water/Sewer Projects - June 13, 2017

Total Project Budget value is all inclusive costs applicable to the project (those capitalized): design, fees, construction, management, inspection, contingencies, etc.  Figure shown includes all moneys previously spent and those currently budgeted for.  Figure does not include moneys earmarked in out years as shown in 5 year CIP focus.

Engineer’s Estimate for Construction does not include contingency.

Construction Phase

Carnelian Sewer Pump Station Rehabilitation (1615):  Full rehabilitation of the Carnelian Main Sewer Pump Station

Status: Contractor (RDC) is preparing for Force Main shut down in order to perform bypass valve installation and force main repair. Work is planned for overnight Sunday night June 18th.  Major system components (pumps, controls, etc.) are on order.  Long duration bypass of the pump station is anticipated from mid-July through October.

·       Percent Complete: 100% (Design), 5% (Construction)

Total Project Budget (Design, Construction, CM/CI): $3,013,590

·       Awarded Bid Amount: $2,702,700

·       Pay requests received: $51,580.25

·       Contract Change Orders: $0

·       Expected Completion Date: November 30, 2017

 

Design / Bid Preparation Phase

 

Natural Gas Generator at Base Facilities:  Installation of a 150kW natural gas back-up generator at District Base facilities.  Project is 75% grant reimbursable up to $150,000.

 

Status:  Bids were opened on June 7, 2017.  See this month’s Board packet for additional information.

·       Percent Complete: 100% (Design), 0% (Construction)

·       Total Project Budget (Design, Construction, CM/CI): $200,000

·       Engineer’s Estimate for Construction: $160,000 (estimate)

·       Expected Bid Date: April 14, 2017

·       Expected Completion Date: October 27, 2017

Carnelian Woods #1 Tank Rehabilitation:  Rehabilitation (recoating & appurtenance clean-up) of the 500,000 CW1 Water Storage Tank.  Project identified 9 years ago when the District hired a contractor to rehabilitate & maintain both the CW1 & CW2 tanks as part of an “initial rehabilitation, inspections, maintenance, and future rehabilitation funding” contract (payments made in quarterly installments).  CW2 was completed and CW1 was pulled from the contract.  Tank still in need of rehabilitation.

Status: Staff is currently working on design/bid documents.

·       Percent Complete: 10% (Design), 0% (Construction)

·       Total Project Budget (Design, Construction, CM/CI):  $350,000

·       Engineer’s Estimate for Construction: TBD (Design/Concept Phase)

·       Expected Bid Date: July 7, 2017 (Award: August 8, 2017)

·       Expected Completion Date: TBD

Lake Intake Pump Improvements:  Improvements and modifications desired for all pumps were identified during emergency pump replacement project.  Due to the sensitivity of these pumps, the necessity of their operation, and the potential difficulty to access during certain times of year, the District is proactively performing system improvements to ensure their continued operation.

Status: Improvements and modifications desired have been identified.

 

·       Percent Complete: 0% (Design), 0% (Construction)

·       Total Project Budget (Design, Construction, CM/CI):  $65,000

·       Engineer’s Estimate for Construction: TBD (Design/Concept Phase)

·       Expected Bid Date: TBD

·       Expected Completion Date: TBD

National Ave. Water Treatment Plant SCADA Improvements – Phase 3:  The 3rd, and final, phase of SCADA upgrades and added improvements.

Status:  Staff has prepared a list of project improvements which include: Documentation, Hardware & Electrical, and Programing.  The majority of these items don’t directly tie together, may be completed independent of the other, and are more “residual clean up” or “maintenance” items.

·       Percent Complete: 10% (Design), 0% (Construction)

·       Total Project Budget (Design, Construction, CM/CI): $175,000

·       Engineer’s Estimate for Construction: TBD (Design/Concept Phase)

·       Expected Bid Date: TBD

·       Expected Completion Date: TBD

Completed Water/Sewer Projects

  • Kingswood Water Main Replacement Project
  • Secline Pump Station Rehabilitation
  • C-1 Wet Well and Dry Well Modifications
  • Carnelian Bay Water West Main Replacement
  • Zone 2 Water Tank Project
  • Tahoe Marina Estates Water Line Replacement Project (In conjunction with Placer County Erosion Control Project)
  • Cutthroat Water Main Replacement
  • Kingswood Booster Pump Station Stairs
  • Dollar Cove Water Treatment Study
  • Lincoln Green Water Line Replacement
  • Kingswood West Tank Security Fence
  • Beaver Street Water and Sewer Line Replacement Project (In conjunction with Placer County Erosion Control Project)