Water/Sewer

Click image to view more photos
Click image to view more photos
Click image to view more photos

The Capital Improvement Program (CIP) directs utility line replacements and specific projects to address current and projected needs of the community’s water and sewer system. Following is a list of Current Projects underway and projects recently completed. Recent bid results are available here.

When the District must relocate the point of service connection for a property, it is the responsibility of the property owner to move their service (water or sewer) to the new point of location.  Additional information on this policy can be found by clicking here.

Current Water/Sewer Projects

Total Project Budget value is all inclusive costs applicable to the project (those capitalized): design, fees, construction, management, inspection, contingencies, etc.  Figure shown includes all moneys previously spent and those currently budgeted for.  Figure does not include moneys earmarked in out years as shown in 5 year CIP focus.

Engineer’s Estimate for Construction does not include contingency.

Construction Phase - Updated March 16, 2016

Base Facilities (1008, 1408 & 1413):  New base facility offices and multipurpose meeting rooms, new public and employee parking areas, site BMPS. 875 National Ave.

Status: Project is complete with the exception of lingering punch list and/or wrap up items currently being worked on.  Staff anticipates one final change order and final budget adjustment at the time of project closeout (i.e. notice of completion) after all change orders have been negotiated and expenses have been reconciled.  Staff met with the contractor on 3-3-2016 to review all outstanding items.  The finalizing of all items and costs will be discussed at a D&P meeting prior to any action.

Percent Complete: 100% (Design), 95% (Construction)

·       Project Budget:

o   PM 1008 – Base Facilities Design & Permitting:        $315,320

o   PM 1408 – Base Facilities BMPs:                            $125,000

o   PM 1413 – Base Facilities Construction:          $4,111,600

Total Combined Project Budget:                             $4,551,920

·       Engineer’s Estimate for Construction: $3,469,421

·       Awarded Bid Amount: $3,626,000

·       Expected Completion Date: Fall 2015

 

Kings Beach Commercial Core (KBCC) Improvements Project (1318): Relocation of sewer and water infrastructure in conflict with KBCC project.

Status:  On hold for the winter months.  All District relocations have been completed for the project, however project close out will not occur until done so by the County.  

Percent Complete: 100% (Design), 95% (Construction)

·       Total Project Budget (Design, Construction, CM/CI): $686,000

·       Engineer’s Estimate for Construction: $420,510 (Not including Outfall areas)

·       Awarded Bid Amount: $727,700

·       Expected Completion Date: Fall 2015

Kings Beach Watershed Improvements Project (1311 & 1317): Relocation of sewer and water infrastructure in conflict with the various Kings Beach Watershed Improvements projects that are outside of the Kings Beach Commercial Core.  These projects consist of the KBCC Outfall areas, Coon Clean Water Pipe (CWP) Improvements Phase 1 Project, and the Lower Chipmunk and Outfall Water Quality Improvement Project.

Status:  The District will be receiving Record Drawings (i.e. as-builts) from the County for these projects in the near future.  

·       Percent Complete: 100% (Design), 95% (Construction).

·       Total Project Budget (Design, Construction, CM/CI): $652,380

·       Engineer’s Estimate for Construction

o   KBCCIP Outfall Areas: $201,775

o   Coon Clean Water Pipe Improvements Phase 1: $36,262

o   Lower Chipmunk and Outfall Water Quality Improvement: $167,270

·       Awarded Bid Amount:

o   KBCCIP Outfall Areas: Costs are included in the KBCC Improvements Project above.

o   Coon Clean Water Pipe Improvements Phase 1: $43,270

o   Lower Chipmunk and Outfall Water Quality Improvement: $159,464

·       Expected Completion Date: Fall 2015

Kings Beach Water Storage Tank Rehabilitation (1510): Rehabilitate (recoat and tank modifications) Kings Beach Tahoe Main system 500,000 gallon tank due to corrosion issues.

Status: The tank is back on line.  Notice of Substantial Completion has been recorded.  Contractor will apply the clear coat in the Spring when weather permits.  There are a few minor warranty items that also need to be completed when weather permits in the Spring. 

Percent Complete: 100% (Design), 99% (Construction)

·  Total Project Budget (Design, Construction, CM/CI): $350,000

·  Engineer’s Estimate for Construction: $200,000

· Awarded Bid Amount: $230,807

· Expected Completion Date: Fall 2015

National Avenue Water Treatment Plant Improvements Phase 2 (1220):  Upgrade system monitors and SCADA instrumentation and controllers.

Status:  The Notice-to-Proceed has been issued with a start date of March 12th and a completion date of June 10th.  Pre-construction site visits have been scheduled for March 8th, and March 17th.

Percent Complete: 100% (Design), 5% (Construction)

Total Project Budget (Design, Construction, CM/CI): $277,000

Engineer’s Estimate for Construction: $142,098

Awarded Bid Amount: $90,475

Expected Completion Date: June 2016

Completed Water/Sewer Projects
  • Kingswood Water Main Replacement Project
  • Secline Pump Station Rehabilitation
  • C-1 Wet Well and Dry Well Modifications
  • Carnelian Bay Water West Main Replacement
  • Zone 2 Water Tank Project
  • Tahoe Marina Estates Water Line Replacement Project (In conjunction with Placer County Erosion Control Project)
  • Cutthroat Water Main Replacement
  • Kingswood Booster Pump Station Stairs
  • Dollar Cove Water Treatment Study
  • Lincoln Green Water Line Replacement
  • Kingswood West Tank Security Fence
  • Beaver Street Water and Sewer Line Replacement Project (In conjunction with Placer County Erosion Control Project)