Water/Sewer

Click image to view more photos
Click image to view more photos
Click image to view more photos

The Capital Improvement Program (CIP) directs utility line replacements and specific projects to address current and projected needs of the community’s water and sewer system. Following is a list of Current Projects underway and projects recently completed. Recent bid results are available here.

Kings Beach Service Relocation Information

 

 

 

 

 

 

Current Water/Sewer Projects - January 17, 2018

Total Project Budget value is all inclusive costs applicable to the project (those capitalized): design, fees, construction, management, inspection, contingencies, etc.  Figure shown includes all moneys previously spent and those currently budgeted for.  Figure does not include money earmarked in out years as shown in 5 year CIP focus.

Engineer’s Estimate for Construction does not include contingency.

Construction Phase

Carnelian Sewer Pump Station Rehabilitation (29-1615):  Full rehabilitation of the Carnelian Main Sewer Pump Station

Status: Pump station has been in full automatic operation since November 29.  Punch list work is progressing.  Final yard paving, restoration of paving on Onyx, and fence repair to be held over to spring of 2018.

·       Percent Complete: 100% (Design), 93% (Construction)

  • Total Project Budget (Design, Construction, CM/CI): $3,013,590

·       Awarded Bid Amount: $2,702,700

·       Progress Payments to Date: $2,424,298

·       Approved Contract Change Orders: $49,900

·       Operational Date: November 29, 2017

 

Carnelian Woods #1 Tank Rehabilitation (39-1819):  Rehabilitation (recoating & appurtenance clean-up) of the 500,000 CW1 Water Storage Tank. 

Status:  Tank rehabilitation and coating project complete.  Tank was returned to service on Monday, November 13, 2017.  All temporary piping and tanks have been removed from site.  See Board report F-3.  This project will be removed from department update next month. 

·       Percent Complete: 100% (Design), 100% (Construction)

·       Total Project Budget (Design, Construction, CM/CI):  $350,000

·       Awarded Bid Amount: $293,250

·       Progress Payments to Date: $288,088

·       Approved Contract Change Orders: $10,000

Tahoe Vista Straightaway Sewer Rehabilitation (MH: SE-1-024 to SE-1-021) (29-1830): Sewer pipe rehabilitation, Length = 840’.

Status:  Construction completed on December 14.  See Board report F-5.  Project will be removed from department update next month.

·       Percent Complete: 100% (Design), 100% (Construction)

·       Total Project Budget (Design, Construction, CM/CI): $100,000

·       Awarded Bid Amount: $66,450

·       Progress Payments to Date: $0 (Invoice for $61,299 in process)

·       Approved Contract Change Orders: -$1,924.95

·       Completion Date: December 14, 2017

Design / Bid Preparation Phase

National Ave. Water Treatment Plant SCADA Improvements – Phase 3:  The 3rd, and final, phase of SCADA upgrades and added improvements.

Status:  Staff has prepared a list of project improvements which include: Documentation, Hardware & Electrical, and Programing.  The majority of these items don’t directly tie together, may be completed independent of the other, and are more “residual clean up” or “maintenance” items.

·       Percent Complete: 10% (Design), 0% (Construction)

·       Total Project Budget (Design, Construction, CM/CI): $175,000

·       Engineer’s Estimate for Construction: TBD (Design/Concept Phase)

·       Expected Bid Date: TBD

·       Expected Completion Date: TBD

Loch Levon & Steelhead Waterlines:  Watermains in these East/West running streets from Deer to East dead end of respective streets.  Continuation of District’s Kings Beach water main replacements installing large diameter mains in County R/W to abandon the existing small diameter backyard mains.

Status:  Plans have been submitted to Placer Co. for encroachment permit.  With Watson Creek Water Main pushed to 2019, District will bid & build these two mains in 2018.  This project’s bid document preparation is also being used as an opportunity to re-write the District’s standard water technical specifications and standard details.

·       Percent Complete: 95% (Design), 0% (Construction)

·       Total Project Budget (Design, Construction, CM/CI): $2,100,000

·       Engineer’s Estimate for Construction: TBD (Design/Concept Phase)

·       Expected Bid Date: Early 2018

·       Expected Completion Date: Summer 2018

Watson Creek Water Main:  Large diameter main from “Garwoods” restaurant to “Watson Creek”.

Status:  District has secured a partnership with Southwest Gas (SWG) to participate in a joint trench venture.  District has committed to providing plans & specs to be incorporated into SWG bid project.  District & SWG have agreed to include water work as a bid alternate whereby depending on the District’s bid costs the District is positioned to either accept or decline the work.  SWG has pushed this project’s schedule to bid/build in 2019.

·       Percent Complete: 0% (Design), 0% (Construction)

·       Total Project Budget (Design, Construction, CM/CI): $1,000,000

·       Engineer’s Estimate for Construction: TBD (Design/Concept Phase)

·       Expected Bid Date: Early 2019

·       Expected Completion Date: Summer 2019

Completed Water/Sewer Projects

  • Kingswood Water Main Replacement Project
  • Secline Pump Station Rehabilitation
  • C-1 Wet Well and Dry Well Modifications
  • Carnelian Bay Water West Main Replacement
  • Zone 2 Water Tank Project
  • Tahoe Marina Estates Water Line Replacement Project (In conjunction with Placer County Erosion Control Project)
  • Cutthroat Water Main Replacement
  • Kingswood Booster Pump Station Stairs
  • Dollar Cove Water Treatment Study
  • Lincoln Green Water Line Replacement
  • Kingswood West Tank Security Fence
  • Beaver Street Water and Sewer Line Replacement Project (In conjunction with Placer County Erosion Control Project)