Water/Sewer

Click image to view more photos
Click image to view more photos
Click image to view more photos

The Capital Improvement Program (CIP) directs utility line replacements and specific projects to address current and projected needs of the community’s water and sewer system. Following is a list of Current Projects underway and projects recently completed. Recent bid results are available here.

Current Water/Sewer Projects

Total Project Budget value is all inclusive costs applicable to the project (those capitalized): design, fees, construction, management, inspection, contingencies, etc.  Figure shown includes all moneys previously spent and those currently budgeted for.  Figure does not include moneys earmarked in out years as shown in 5 year CIP focus.

Engineer’s Estimate for Construction does not include contingency

Construction Phase

Base Facilities (1008, 1408 & 1413):  New base facility offices and multipurpose meeting rooms, new public and employee parking areas, site BMPS. 875 National Ave.

Status: Site work has continued with the water and sewer line both being installed and the electrical conduits to and from the building are installed to the transformer.  The building framing is 95% complete with only exterior overhangs and some interior shear wall to be completed.  Doorframes and windows are installed and drywall is stocked and will begin this week following the installation of insulation.  An updated schedule is expected shortly to help the District to finalize the building move-in date.

·       Percent Complete: 100% (Design), 55% (Construction)

·       Total Project Budget (Design, Construction, CM/CI): $4,370,620

·       Engineer’s Estimate for Construction: $3,469,421

·       Awarded Bid Amount: $3,626,000

·       Expected Completion Date: Fall 2015

Kings Beach Commercial Core (KBCC) Improvements Project (1311, 1317, 1318): Relocation of sewer and water infrastructure in conflict with KBCC project.

Status:  Construction has begun for the 2015 season.  District staff (operations crew and management) has been maintaining contact with the contractor and District hired CM/CI personnel during all stages. 

·       Percent Complete: 100% (Design), 50% (Construction).

·       Total Project Budget (Design, Construction, CM/CI): $1,150,830

·       Engineer’s Estimate for Construction: $824,950

·       Awarded Bid Amount: $667,700

·       Expected Completion Date: Fall 2015

Dollar Hill 22” Force Main Rehabilitation (1407): Rehabilitate (slip-line) existing original Dollar force main due to deteriorated conditions.

Status: Submittals are being reviewed by staff and the engineer.  Staff and the engineer are reviewing a submitted alternate for the couplings which, depending on approval, will determine the final schedule for the project due to lead times.  Project is anticipated to be mostly night work and will be completed this summer.

·       Percent Complete: 100% (Design), 0% (Construction)

·       Total Project Budget (Design, Construction, CM/CI): $812,954

·       Engineer’s Estimate for Construction: $674,400

·       Awarded Bid Amount: $688,000

·       Expected Completion Date: Summer 2015

 

Completed Water/Sewer Projects

  • Kingswood Water Main Replacement Project
  • Secline Pump Station Rehabilitation
  • C-1 Wet Well and Dry Well Modifications
  • Carnelian Bay Water West Main Replacement
  • Zone 2 Water Tank Project
  • Tahoe Marina Estates Water Line Replacement Project (In conjunction with Placer County Erosion Control Project)
  • Cutthroat Water Main Replacement
  • Kingswood Booster Pump Station Stairs
  • Dollar Cove Water Treatment Study
  • Lincoln Green Water Line Replacement
  • Kingswood West Tank Security Fence
  • Beaver Street Water and Sewer Line Replacement Project (In conjunction with Placer County Erosion Control Project)