Water/Sewer

Click image to view more photos
Click image to view more photos
Click image to view more photos

The Capital Improvement Program (CIP) directs utility line replacements and specific projects to address current and projected needs of the community’s water and sewer system. Following is a list of Current Projects underway and projects recently completed. Recent bid results are available here.

Kings Beach Service Relocation Information

 

 

 

 

 

 

Current Water/Sewer Projects - July 19, 2018

Total Project Budget value is all inclusive costs applicable to the project (those capitalized): design, fees, construction, management, inspection, contingencies, etc.  Figure shown includes all moneys previously spent and those currently budgeted for.  Figure does not include money earmarked in out years as shown in 5 year CIP focus.

Engineer’s Estimate for Construction does not include contingency.

Construction Phase

Carnelian Sewer Pump Station Rehabilitation (29-1615):  Full rehabilitation of the Carnelian Main Sewer Pump Station

Status: Final site clean-up continues.  Anticipate Notice of Completion next month.

·       Percent Complete: 100% (Design), 98% (Construction)

  • Total Project Budget (Design, Construction, CM/CI): $3,013,590

·       Awarded Bid Amount: $2,702,700

·       Progress Payments to Date: $2,574,315

·       Approved Contract Change Orders: $47,105.37

·       Operational Date: November 29, 2017

 

Loch Levon & Steelhead Waterlines:  Loch Levon: from Deer to Chipmunk.  Steelhead: from Deer to East dead end.  Continuation of District’s Kings Beach water main replacements installing large diameter mains in County R/W to abandon the existing small diameter backyard mains.  Project Statistics:

5,491’ of 8” Watermain

8 Fire hydrants

148 Services

9 Connections to existing 6” mains

27 Valves

Asphalt Slurry both streets, full width

Status:

Installed: 1,400 LF Main, 12 Services, 2 Fire Hydrants, 5 Valve Clusters.

·       Percent Complete: 100% (Design), 21% (Construction)

·       Total Project Budget (Design, Construction, CM/CI, etc.): $2,200,000

·       Awarded Bid Amount: $1,920,029.10

·       Progress Payments to Date: $390,576.19

·       Approved Contract Change Orders: $65,203.73

·       Expected Completion Date: September 15, 2018

 

Completed Water/Sewer Projects

  • Kingswood Water Main Replacement Project
  • Secline Pump Station Rehabilitation
  • C-1 Wet Well and Dry Well Modifications
  • Carnelian Bay Water West Main Replacement
  • Zone 2 Water Tank Project
  • Tahoe Marina Estates Water Line Replacement Project (In conjunction with Placer County Erosion Control Project)
  • Cutthroat Water Main Replacement
  • Kingswood Booster Pump Station Stairs
  • Dollar Cove Water Treatment Study
  • Lincoln Green Water Line Replacement
  • Kingswood West Tank Security Fence
  • Beaver Street Water and Sewer Line Replacement Project (In conjunction with Placer County Erosion Control Project)