Water/Sewer

Click image to view more photos
Click image to view more photos
Click image to view more photos

The Capital Improvement Program (CIP) directs utility line replacements and specific projects to address current and projected needs of the community’s water and sewer system. Following is a list of Current Projects underway and projects recently completed. Recent bid results are available here.

Kings Beach Service Relocation Information

 

 

 

 

 

 

Current Water/Sewer Projects - April 25, 2018

Total Project Budget value is all inclusive costs applicable to the project (those capitalized): design, fees, construction, management, inspection, contingencies, etc.  Figure shown includes all moneys previously spent and those currently budgeted for.  Figure does not include money earmarked in out years as shown in 5 year CIP focus.

Engineer’s Estimate for Construction does not include contingency.

Construction Phase

Carnelian Sewer Pump Station Rehabilitation (29-1615):  Full rehabilitation of the Carnelian Main Sewer Pump Station

Status: Final yard paving, restoration of paving on Onyx, fence repair and punchlist items have been held over until spring.  Tentative completion date of May 15, 2018.

·       Percent Complete: 100% (Design), 93% (Construction)

  • Total Project Budget (Design, Construction, CM/CI): $3,013,590

·       Awarded Bid Amount: $2,702,700

·       Progress Payments to Date: $2,424,298

·       Approved Contract Change Orders: $37,649.75

·       Operational Date: November 29, 2017

 

Loch Levon & Steelhead Waterlines:  Loch Levon: from Deer to Chipmunk.  Steelhead: from Deer to East dead end.  Continuation of District’s Kings Beach water main replacements installing large diameter mains in County R/W to abandon the existing small diameter backyard mains.

Status:  Bid opened 3/27/2018.  See Report G-3.  Project statistics:

5,491’ of 8” Watermain

8 Fire hydrants

148 Services

9 Connections to existing 6” mains

27 Valves

Asphalt Slurry both streets, full width

·       Percent Complete: 100% (Design), 0% (Construction)

·       Total Project Budget (Design, Construction, CM/CI, etc.): $2,100,000

·       Awarded Bid Amount (anticipated per G-3): $1,920,029

·       Progress Payments to Date: $0

·       Approved Contract Change Orders: $0

·       Expected Completion Date: September 15, 2018

Design / Bid Preparation Phase

National Ave. Water Treatment Plant SCADA Improvements – Phase 3:  The 3rd, and final, phase of SCADA upgrades and added improvements.

Status:  Staff has prepared a list of project improvements which include: Documentation, Hardware & Electrical, and Programing.  The majority of these items don’t directly tie together, may be completed independent of the other, and are more “residual clean up” or “maintenance” items.

·       Percent Complete: 10% (Design), 0% (Construction)

·       Total Project Budget (Design, Construction, CM/CI): $175,000

·       Engineer’s Estimate for Construction: TBD (Design/Concept Phase)

·       Expected Bid Date: TBD

·       Expected Completion Date: TBD

Park Gazebo :  Rebuild of shade structure at tennis courts/ dog park which collapsed during Winter of 2016-2017.

Status:  Site Plans prepared (in house). Structural design is under way by Gazebo manufacturer.  Expect to bid and construct during summer of 2018.

·       Percent Complete: 33% (Design), 0% (Construction)

·       Total Project Budget (Design, Construction, CM/CI): $34,515

·       Engineer’s Estimate for Construction: $34,515

·       Expected Bid Date: June 5, 2018

·       Expected Completion Date: October 15, 2018

Completed Water/Sewer Projects

  • Kingswood Water Main Replacement Project
  • Secline Pump Station Rehabilitation
  • C-1 Wet Well and Dry Well Modifications
  • Carnelian Bay Water West Main Replacement
  • Zone 2 Water Tank Project
  • Tahoe Marina Estates Water Line Replacement Project (In conjunction with Placer County Erosion Control Project)
  • Cutthroat Water Main Replacement
  • Kingswood Booster Pump Station Stairs
  • Dollar Cove Water Treatment Study
  • Lincoln Green Water Line Replacement
  • Kingswood West Tank Security Fence
  • Beaver Street Water and Sewer Line Replacement Project (In conjunction with Placer County Erosion Control Project)