Water/Sewer

Click image to view more photos
Click image to view more photos
Click image to view more photos

The Capital Improvement Program (CIP) directs utility line replacements and specific projects to address current and projected needs of the community’s water and sewer system. Following is a list of Current Projects underway and projects recently completed. Recent bid results are available here.

Current Water/Sewer Projects

Total Project Budget value is all inclusive costs applicable to the project (those capitalized): design, fees, construction, management, inspection, contingencies, etc.  Figure shown includes all moneys previously spent and those currently budgeted for.  Figure does not include moneys earmarked in out years as shown in 5 year CIP focus.

Engineer’s Estimate for Construction does not include contingency.

Construction Phase - Updated July 14, 2015

Base Facilities (1008, 1408 & 1413):  New base facility offices and multipurpose meeting rooms, new public and employee parking areas, site BMPS. 875 National Ave.

Status: Work is continuing on both the inside and the outside of the new base facilities.  Painting is complete which will allow multiple other interior finishes to start work this week including but not limited to; Flooring, Cabinets, Electrical Trim, Hvac Trim, Grid Ceiling and the Elevator.  The site sidewalk will also be installed this week around the front and side of the building.  The move in date has been locked in and is scheduled on Aug 4th as the Elevator is scheduled to be completed and inspected the week prior.

·       Percent Complete: 100% (Design), 65% (Construction)

·       Project Budget:

o   PM 1008 – Base Facilities Design & Permitting:        $315,320

o   PM 1408 – Base Facilities BMPs:                            $125,000

o   PM 1413 – Base Facilities Construction:          $4,111,600

Total Combined Project Budget:                             $4,551,920

·       Engineer’s Estimate for Construction: $3,469,421

·       Awarded Bid Amount: $3,626,000

·       Expected Completion Date: Fall 2015

 

Kings Beach Commercial Core (KBCC) Improvements Project (1311, 1317, 1318): Relocation of sewer and water infrastructure in conflict with KBCC project.

Status:  Construction continues for the 2015 season.  A majority of the work is service related.  District staff (operations crew and management) has been maintaining contact with the contractor and District hired CM/CI personnel during all stages.  

·       Percent Complete: 100% (Design), 60% (Construction).

·       Total Project Budget (Design, Construction, CM/CI): $1,150,830

·       Engineer’s Estimate for Construction: $824,950

·       Awarded Bid Amount: $667,700

·       Expected Completion Date: Fall 2015

Dollar Hill 22” Force Main Rehabilitation (1407): Rehabilitate (slip-line) existing original Dollar force main due to deteriorated conditions.

Status: The new force main pipe is fully installed and operational.  With the exception of placing an added slurry coat on the road the project is complete. 

·       Percent Complete: 100% (Design), 99% (Construction)

·       Total Project Budget (Design, Construction, CM/CI): $812,954

·       Engineer’s Estimate for Construction: $674,400

·       Awarded Bid Amount: $688,000

·       Expected Completion Date: Summer 2015

 

Kings Beach Water Storage Tank Rehabilitation (1510): Rehabilitate (recoat and tank modifications) Kings Beach Tahoe Main system 500,000 gallon tank due to corrosion issues.

Status:  A pre-construction meeting was held on July 10th with the contractor, design engineer, coating inspector, and District staff.  Construction is anticipated to begin the week of July 13th.

·       Percent Complete: 100% (Design), 0% (Construction)

·       Total Project Budget (Design, Construction, CM/CI): $350,000

·       Engineer’s Estimate for Construction: $200,000

·       Awarded Bid Amount: $230,807

·       Expected Completion Date: Fall 2015

 

Completed Water/Sewer Projects

  • Kingswood Water Main Replacement Project
  • Secline Pump Station Rehabilitation
  • C-1 Wet Well and Dry Well Modifications
  • Carnelian Bay Water West Main Replacement
  • Zone 2 Water Tank Project
  • Tahoe Marina Estates Water Line Replacement Project (In conjunction with Placer County Erosion Control Project)
  • Cutthroat Water Main Replacement
  • Kingswood Booster Pump Station Stairs
  • Dollar Cove Water Treatment Study
  • Lincoln Green Water Line Replacement
  • Kingswood West Tank Security Fence
  • Beaver Street Water and Sewer Line Replacement Project (In conjunction with Placer County Erosion Control Project)