Water/Sewer

Click image to view more photos
Click image to view more photos
Click image to view more photos

The Capital Improvement Program (CIP) directs utility line replacements and specific projects to address current and projected needs of the community’s water and sewer system. Following is a list of Current Projects underway and projects recently completed. Recent bid results are available here.

When the District must relocate the point of service connection for a property, it is the responsibility of the property owner to move their service (water or sewer) to the new point of location.  Additional information on this policy can be found by clicking here.

Current Water/Sewer Projects

Total Project Budget value is all inclusive costs applicable to the project (those capitalized): design, fees, construction, management, inspection, contingencies, etc.  Figure shown includes all moneys previously spent and those currently budgeted for.  Figure does not include moneys earmarked in out years as shown in 5 year CIP focus.

Engineer’s Estimate for Construction does not include contingency.

Construction Phase - Updated December 14, 2015

Base Facilities (1008, 1408 & 1413):  New base facility offices and multipurpose meeting rooms, new public and employee parking areas, site BMPS. 875 National Ave.

Status: The landscape is complete along with the site BMP’s.  NPT has been filed with Lahontan Waterboard.  Punch list items are being worked on.  Significant electrical work still needs to be completed on the shop and the annex but this work cannot go forward until Liberty Energy installs the transformer to feed both of the building.  Liberty is currently working on this.

Percent Complete: 100% (Design), 95% (Construction)

·       Project Budget:

o   PM 1008 – Base Facilities Design & Permitting:        $315,320

o   PM 1408 – Base Facilities BMPs:                            $125,000

o   PM 1413 – Base Facilities Construction:          $4,111,600

Total Combined Project Budget:                             $4,551,920

·       Engineer’s Estimate for Construction: $3,469,421

·       Awarded Bid Amount: $3,626,000

·       Expected Completion Date: Fall 2015

 

Kings Beach Commercial Core (KBCC) Improvements Project (1318): Relocation of sewer and water infrastructure in conflict with KBCC project.

Status:  Construction is wrapping up for the 2015 season with punch list items being fulfilled.  District staff (operations crew and management) has been maintaining contact with the contractor and CM/CI personnel during all stages.  

Percent Complete: 100% (Design), 85% (Construction)

·       Total Project Budget (Design, Construction, CM/CI): $686,000

·       Engineer’s Estimate for Construction: $420,510 (Not including Outfall areas)

·       Awarded Bid Amount: $727,700

·       Expected Completion Date: Fall 2015

 

Kings Beach Watershed Improvements Project (1311 & 1317): Relocation of sewer and water infrastructure in conflict with the various Kings Beach Watershed Improvements projects that are outside of the Kings Beach Commercial Core.  These projects consist of the KBCC Outfall areas, Coon Clean Water Pipe (CWP) Improvements Phase 1 Project, and the Lower Chipmunk and Outfall Water Quality Improvement Project.

Status:  KBCCIP Outfall area relocations are occurring as part of the KBCCIP (see above), Coon CWP project is complete, and Lower Chipmunk has been completed with punch list items currently being fulfilled.  District staff (operations crew and management) has been maintaining contact with the contractor and CM/CI personnel during all stages  

·       Percent Complete: 100% (Design), 85% (Construction).

·       Total Project Budget (Design, Construction, CM/CI): $652,380

·       Engineer’s Estimate for Construction

o   KBCCIP Outfall Areas: $201,775

o   Coon Clean Water Pipe Improvements Phase 1: $36,262

o   Lower Chipmunk and Outfall Water Quality Improvement: $167,270

·       Awarded Bid Amount:

o   KBCCIP Outfall Areas: Costs are included in the KBCC Improvements Project above.

o   Coon Clean Water Pipe Improvements Phase 1: $43,270

o   Lower Chipmunk and Outfall Water Quality Improvement: $159,464

·       Expected Completion Date: Fall 2015

 

Kings Beach Water Storage Tank Rehabilitation (1510): Rehabilitate (recoat and tank modifications) Kings Beach Tahoe Main system 500,000 gallon tank due to corrosion issues.

Status: Interior and exterior coatings are complete.  Chlorination of the tank is complete.  The tank will should be back on line within the next 2 weeks, subject to passing bacteriological tests.

Percent Complete: 100% (Design), 90% (Construction)

·       Total Project Budget (Design, Construction, CM/CI): $350,000

·       Engineer’s Estimate for Construction: $200,000

·       Awarded Bid Amount: $230,807

·       Expected Completion Date: Fall 2015

 

Completed Water/Sewer Projects

  • Kingswood Water Main Replacement Project
  • Secline Pump Station Rehabilitation
  • C-1 Wet Well and Dry Well Modifications
  • Carnelian Bay Water West Main Replacement
  • Zone 2 Water Tank Project
  • Tahoe Marina Estates Water Line Replacement Project (In conjunction with Placer County Erosion Control Project)
  • Cutthroat Water Main Replacement
  • Kingswood Booster Pump Station Stairs
  • Dollar Cove Water Treatment Study
  • Lincoln Green Water Line Replacement
  • Kingswood West Tank Security Fence
  • Beaver Street Water and Sewer Line Replacement Project (In conjunction with Placer County Erosion Control Project)