Water/Sewer

Click image to view more photos
Click image to view more photos
Click image to view more photos

The Capital Improvement Program (CIP) directs utility line replacements and specific projects to address current and projected needs of the community’s water and sewer system. Following is a list of Current Projects underway and projects recently completed. Recent bid results are available here.

Kings Beach Service Relocation Information

NTPUD service relocation

 

 

 

 

 

 

Current Water/Sewer Projects - January 11, 2019

Total Project Budget value is all inclusive costs applicable to the project (those capitalized): design, fees, construction, management, inspection, contingencies, etc.  Figure shown includes all moneys previously spent and those currently budgeted for.  Figure does not include money earmarked in out years as shown in 5 year CIP focus.

Engineer’s Estimate for Construction does not include contingency.

Typically we only list projects in the construction phase but with construction wrapped up for the winter and next year's projects in planning, we have included those for your information.  

Construction Phase

 

Loch Levon & Steelhead Waterlines:  Loch Levon:  from Deer to Chipmunk.  Steelhead:  from Deer to East dead end. Continuation of District’s Kings Beach water main replacements installing large diameter mains in County R/W to abandon the existing small diameter backyard mains. Project Statistics:

5,491’ of 8” Watermain

8 Fire hydrants

148 Services

9 Connections to existing 6” mains

27 Valves

Asphalt Slurry both streets, full width

Status:

All Water infrastructure is installed, except six services at the Steelhead/Fox intersection potentially requiring a modified installation approach pending easement solidification (TBD).  Remaining items to complete are: minor punch-list items, the six services noted above, and final slurry seal.  Project on Winter hold.

·       Percent Complete:  100% (Design), 96% (Construction) 

·       Total Project Budget (Design, Construction, CM/CI, etc.):  $2,250,000

·       Awarded Bid Amount:  $1,920,029.10

·       Progress Payments to Date:  $1,893,366.36

·       Approved Contract Change Orders:  $127,044.12

·       Expected Completion Date:  June 30, 2019.

Gravity System Rehabilitation:  Cured in Place Pipe lining of select gravity mains (standing biennial project). Mains for standing project determined through latest/greatest grading assessment immediately ahead of bid.  Mains to be completed this project round are Loch Levon & Steelhead.

Status:  Project awarded to Southwest Pipeline & Trenchless Corporation.  Contractor’s schedule currently to be determined.  Staff is soliciting special inspection services proposals in anticipation for award at February’s Board meeting.

·       Percent Complete:  100% (Design), 0% (Construction)

·       Total Project Budget (Design, Construction, CM/CI):  $792,000

·       Awarded Bid Amount:  $443,936

·       Progress Payments to Date:  $0

·       Approved Contract Change Orders:  $0

·       Expected Completion Date:  TBD

Active Design / Bid Preparation Phase

National Sewer Pump Station Rehabilitation:  Full rehabilitation of Sewer pump station.  This is the last of four (4) main pump stations to receive full rehabilitation in this current rehabilitation cycle.

Status:  Site survey underway.

·       Percent Complete:  0% (Design), 0% (Construction)

·       Total Current Project Budget (Design, Construction, CM/CI):  $180,035

·       Engineer’s Estimate for Construction:  TBD

·       Bid Opening:  TBD

·       Expected Completion Date:  TBD

North Tahoe Regional Park Trailhead:  Multi-Use Trailhead improvements (upper parking lot) & Multi-use ADA trail from lower restrooms to tennis courts.

These projects anticipate grant funding: Multi-Use Trailhead – Truckee Tahoe Airport District (TTAD), Multi-use Trail – Placer County.  The District entered into a partnership agreement with the TTAD in May 2018 for $320,000 in grant funds and has received $160,000 of the funds with the balance to be received in May 2019.  Staff submitted a grant application for $200,000 of Placer County Area 1 Park Dedication Fees to the North Tahoe Regional Advisory Council which recommended it to the Parks and Recreation Commission for consideration.

Status:  90% plans submitted.  Comments generated and submitted to design consultant to incorporation into final (100%) plans/specs/estimate.

·       Percent Complete:  0% (Design), 0% (Construction)

·       Total Current Project Budget (Design, Construction, CM/CI):  $515,000

·       Engineer’s Estimate for Construction:  $515,000

·       Bid Opening:  March 2019

·       Expected Completion Date:  May 2019

Park Gazebo:  Rebuild of shade structure at tennis courts/dog park which collapsed during Winter of 2016-2017. This project is FEMA grant funded.

Status:  No Bids were received through second bid process.  Project is now being incorporated into Regional Parks Trailhead project.  Grant extension has been approved through August 16, 2019.

·       Percent Complete: 100% (Design), 0% (Construction)

·       Total Project Budget (Design, Construction, CM/CI):  $34,515

·       Engineer’s Estimate for Construction:  $34,515

·       Bid Opening:  December 19, 2018

·       Expected Completion Date:  TBD

National Ave. SCADA Improvements – Phase 3:  Final phase addressing clean up and maintenance items to complete project.

Status:  Project scoping under review by staff.

·       Percent Complete: 25% (Design), 0% (Construction)

·       Total Project Budget (Design, Construction, CM/CI):  $175,000

·       Engineer’s Estimate for Construction:  TBD

·       Bid Opening:  TBD

·       Expected Completion Date:  TBD

Completed Water/Sewer Projects

  • Kingswood Water Main Replacement Project
  • Secline Pump Station Rehabilitation
  • C-1 Wet Well and Dry Well Modifications
  • Carnelian Bay Water West Main Replacement
  • Zone 2 Water Tank Project
  • Tahoe Marina Estates Water Line Replacement Project (In conjunction with Placer County Erosion Control Project)
  • Cutthroat Water Main Replacement
  • Kingswood Booster Pump Station Stairs
  • Dollar Cove Water Treatment Study
  • Lincoln Green Water Line Replacement
  • Kingswood West Tank Security Fence
  • Beaver Street Water and Sewer Line Replacement Project (In conjunction with Placer County Erosion Control Project)